title: "Create a purchase order"
space: "OLY ERP Docs"
url: "https://oly.et/olyerpdocs/buying/purchase-order"
updated: "2026-10-18"
---

A **Purchase Order** is your confirmed order to a supplier. It records what you will receive, at what price and by when. It does not change stock or accounts until goods are received and billed.

## Before you start

- The supplier and items exist.
- A submitted **Material Request** or **Supplier Quotation**, if your company uses them. Creating from them saves typing.

## Create from a material request or supplier quotation

1. Open the submitted **Material Request** (or **Supplier Quotation**).
2. Click **Create > Purchase Order**.
3. Choose the **Supplier** if it is not filled in.
4. Check the items, quantities and rates. Then continue from step 5 below.

## Create directly

1. Go to **Buying > Purchase Order** and click **+ Add Purchase Order**.
2. Choose the **Supplier**, for example "Example Grain Supplier PLC".
3. Set **Required By**, for example 2026-10-25.
4. In **Items**, add each **Item Code**, **Quantity** and **Rate**. Example: "Corn grits", 2,500 Kg at 40 ETB per Kg = 100,000 ETB.
5. Check the **Set Target Warehouse**, for example "Raw Materials - EF".
6. In **Taxes and Charges**, choose the **Purchase Taxes and Charges Template**, for example "VAT 15%". Your OLY ERP consultant sets this up during onboarding. In the example, VAT is 15,000 ETB and the **Grand Total** is 115,000 ETB.
7. Check the **Payment Schedule**, which comes from the supplier's payment terms.
8. Click **Save**, then **Submit**.
9. Click **Print** or email the order to the supplier.

## What happens next

From the submitted purchase order, use **Create**:

- **Create > Purchase Receipt** when the goods arrive.
- **Create > Purchase Invoice** when the supplier's invoice arrives.
- **Create > Payment** if you pay in advance.

The status shows progress: **To Receive and Bill**, **To Bill**, **To Receive** or **Completed**.

## Good to know

- Your company may need a manager to approve purchase orders above an amount. Your consultant sets up any approval steps.
- To change a submitted order, use **Update Items** if your role allows it, or **Cancel** and **Amend**.
- If the supplier cannot deliver the rest, click **Close** so the remaining quantity is no longer pending.
- The price on the order carries to the receipt and invoice. Check it against the supplier's offer before you submit.

## Related

- [Request materials (material request)](/olyerpdocs/buying/material-request)
- [Receive goods (purchase receipt)](/olyerpdocs/buying/purchase-receipt)
- [Record a supplier invoice (with VAT and withholding)](/olyerpdocs/buying/purchase-invoice)