title: "Recipes: bill of materials (BOM)"
space: "OLY ERP Docs"
url: "https://oly.et/olyerpdocs/manufacturing/bom"
updated: "2026-10-18"
---

A **BOM** (Bill of Materials) is the recipe for a product. It says what goes into a fixed quantity of the product. Every work order uses a BOM to know what materials to issue and what the product costs.

## Before you start

- The finished good and all raw materials and packaging exist as items.
- Know the real recipe for one production run, including packaging and normal losses.

## Steps

### Create a BOM

1. Go to **Manufacturing > BOM** and click **+ Add BOM**.
2. In **Item**, choose the finished good, for example "Corn snack 50 g, cheese".
3. In **Quantity**, enter the quantity this recipe makes, for example 1,000 (packs).
4. In **Rate Of Materials Based On**, choose how materials are costed, usually **Valuation Rate** (what you paid). Your consultant may set this for you.
5. In the **Items** table, add each ingredient and packaging item with the quantity for 1,000 packs:

| Item | Qty | Unit |
|---|---|---|
| Corn grits | 42 | Kg |
| Sunflower oil | 8 | Litre |
| Cheese seasoning | 4 | Kg |
| Printed film, cheese | 3 | Kg |
| Carton | 21 | Nos |

6. Click **Save**. Check the costs (see below).
7. Click **Submit**. Only a submitted BOM can be used in a work order.

### Record scrap and normal loss

Some material is always lost: broken snacks, corn dust, film trim.

1. In the **Scrap & Process Loss** section, add a row in **Scrap Items** for anything you keep or sell, for example "Broken snacks", 2 Kg, with its rate.
2. If part of the output is simply lost, enter the **% Process Loss**.

Scrap items go into stock when you record production. Their value reduces the cost of the finished good.

### Check the cost

After saving, the **Costing** section shows **Raw Material Cost**, **Scrap Material Cost** and **Total Cost**. Divide the total by the BOM quantity to get the cost per pack. Example: total ETB 9,885 for 1,000 packs = about ETB 9.89 per pack (example prices only).

When material prices change, open the submitted BOM and click **Update Cost** to refresh the figures.

### Change a recipe (versions)

You cannot edit a submitted BOM's items. To change a recipe:

1. Open the current BOM, click the **...** menu and choose **Duplicate**. Or create a new BOM for the same item.
2. Change the quantities and submit the new BOM.
3. Tick **Is Default** on the new BOM, so new work orders use it.
4. On the old BOM, untick **Is Active** when you no longer want anyone to use it.

## Good to know

- One item can have many BOMs, for example a trial recipe and the standard one. Only one is the default.
- Write the recipe for a real run size (for example 1,000 packs). Small quantities give rounding errors.
- Include packaging in the BOM. If you forget the film and cartons, their stock will never go down.
- **With Operations** adds steps (mixing, frying, packing) and Job Cards. Leave it off unless you want to track each step.
- Old work orders keep the BOM they were made with. A new default only affects new work orders.

## Related

- [Raw materials, packaging and finished goods items](/olyerpdocs/manufacturing/items-for-production)
- [Produce with a work order](/olyerpdocs/manufacturing/work-order)
- [Manufacturing reports](/olyerpdocs/manufacturing/manufacturing-reports)