OLY ERP has ready-made reports for production. Use them to plan runs, find delays and spot waste. Open any report from the search bar by typing its name, or from the **Reports** area of the Manufacturing workspace.

## Before you start

- Reports only show what was recorded. Submit work orders and stock entries on the day they happen.
- You need a production or stock role to open these reports.

## The reports

### Production Analytics: how many work orders, and their status

Shows work orders per week, month or quarter, grouped by status (for example not started, overdue, pending, completed).

1. Open **Production Analytics**.
2. Set **From Date**, **To Date** and **Range** (for example Monthly).
3. Look for a growing number of overdue work orders.

### Work Order Summary: progress of each work order

Lists work orders with item, quantity to make, quantity made and status.

1. Open **Work Order Summary**.
2. Filter by date, **Status** or **Production Item**.
3. Use it in the weekly production meeting to see what is late.

### BOM Stock Report: can we make this run?

Shows, for one BOM, how much of each material is needed and how much is in stock.

1. Open **BOM Stock Report**.
2. Choose the **BOM**, the **Warehouse** (for example "Raw Materials - EF") and the **Quantity to Produce**.
3. Rows that are short tell Dawit what to buy before the run.

### BOM cost and recipe reports

- Open a submitted **BOM** to see its **Costing** section (raw material cost, scrap and total cost). Click **Update Cost** after price changes.
- **BOM Explorer** shows every material in a BOM, including materials of sub-recipes.
- **BOM Variance Report** compares, per work order, the **Required Qty** from the recipe with the **Consumed Qty**. Big differences mean waste, wrong recipes or wrong entries.

### Stock Projected Qty: what stock will we have?

Shows for each item and warehouse the actual quantity plus what is ordered, planned and reserved, as a **Projected Qty**.

1. Open **Stock Projected Qty**.
2. Filter by **Warehouse** or **Item Group**, for example "Raw Material".
3. A negative projected quantity means open work orders or sales orders need more than you have or have ordered.

## Good to know

- Open work orders that will never be finished make every report wrong. Close them with **Status > Close**.
- All reports can be filtered, printed and exported to Excel from the report menu.
- For stock per batch and expiry, use **Batch-wise Balance History** from the Stock reports.
- Your consultant can add a report to your workspace if you use it every day.

## Related

- [Produce with a work order](/olyerpdocs/manufacturing/work-order)
- [Recipes: bill of materials (BOM)](/olyerpdocs/manufacturing/bom)
- [Stock reports: balance, movements and ageing](/olyerpdocs/stock/stock-reports)