title: "Produce with a work order"
space: "OLY ERP Docs"
url: "https://oly.et/olyerpdocs/manufacturing/work-order"
updated: "2026-10-18"
---

A **Work Order** tells the factory to make a quantity of one product, using one BOM. It tracks what materials were issued, what was produced and what is still to come.

## Before you start

- The product has a submitted, default **BOM**.
- The materials are in stock in the store, or will arrive before the run.
- Your consultant has set the default **Work-in-Progress Warehouse** and **Target Warehouse** for production.

## Steps

### 1. Plan the run

1. Go to **Manufacturing > Work Order** and click **+ Add Work Order**.
2. In **Item To Manufacture**, choose "Corn snack 50 g, cheese". The **BOM No** fills in from the default BOM.
3. Enter **Qty To Manufacture**, for example 4,800 (100 cartons).
4. Check the warehouses: **Source Warehouse** (where materials come from), **Work-in-Progress Warehouse** ("Work In Progress - EF") and **Target Warehouse** ("Finished Goods - EF").
5. Enter the **Planned Start Date**.
6. Check the **Required Items** table. OLY ERP has worked out the materials from the BOM.
7. Click **Save**, then **Submit**. The status is **Not Started**.

### 2. Transfer materials to the line

1. On the submitted work order, click **Start**.
2. Confirm the quantity to transfer for. OLY ERP opens a **Stock Entry** of type **Material Transfer for Manufacture**.
3. Abebe checks each row: item, quantity, source warehouse and batch. Change a batch if he is picking a different lot.
4. Click **Save**, then **Submit**. Materials move to "Work In Progress - EF". The work order status becomes **In Process**.

### 3. Finish production

1. When the run is done, open the work order and click **Finish**.
2. Enter the quantity actually produced, for example 4,750 packs.
3. OLY ERP opens a **Stock Entry** of type **Manufacture**. It shows the materials used (from Work In Progress) and the finished good row (into Finished Goods).
4. Check the finished good row: quantity and batch. Check any scrap rows.
5. Click **Save**, then **Submit**. Stock of finished packs goes up and materials go down.

### Partial production

You do not have to finish the whole quantity at once.

- Click **Finish** with the quantity made so far, for example 2,400 on day one. The status stays **In Process**.
- Click **Finish** again for the rest on day two. When **Manufactured Qty** reaches **Qty To Manufacture**, the status becomes **Completed**.
- If you will not make the rest, use **Status > Stop** (can be re-opened) or **Status > Close** (final).

## Good to know

- Always use **Start** and **Finish** on the work order. A plain stock transfer is not linked to the work order.
- If you issued more material than you used, return it to the store before you close the work order. Ask your consultant how your setup handles leftovers.
- If the BOM has operations, OLY ERP also creates **Job Cards**. Each step on the line is recorded on its Job Card.
- A work order linked to a **Sales Order** shows the customer it is for. You can create it from the sales order.

## Related

- [How production works in OLY ERP](/olyerpdocs/manufacturing/production-flow)
- [Batches, expiry and traceability for produced goods](/olyerpdocs/manufacturing/production-batches)
- [Recipes: bill of materials (BOM)](/olyerpdocs/manufacturing/bom)